Research · May 2026

Federal Tax Cliff Threatens Pennsylvania's Energy Generation Pipeline

91 Pennsylvania generation projects — 1,758 MW of summer-peak capacity — have signed PJM Interconnection Agreements and are ready to build. They are stuck on state and local permitting. For the solar and wind subset, the One Big Beautiful Bill Act's federal tax credit deadlines threaten to void project economics within 14 months. Governor Shapiro's HB 502 is the obvious vehicle, but its 25 MW eligibility threshold excludes most of the projects at risk. This is the case for lowering it to 10 MW — or lower.

Pennsylvania's active interconnection queue is overwhelmingly clean energy. Solar, storage, and solar+storage hybrids together account for 84% of the 10,400 MW pipeline. Natural gas is 4%. Whether Pennsylvania captures or forfeits this generation depends on Harrisburg. — Build Philly Now analysis of PJM Planning Queues data

What's in the queuePennsylvania's pipeline is not what people think it is

Active PA queue by fuel

Summer-peak capacity, all 340 active development projects (10,421 MW total)

Status of GIA-posted projects

22 are suspended — most likely behind state or local permitting

Top counties by stuck capacity

Bar color reflects party of the state senator representing each county. Almost all of these counties are represented by Republicans.

ComparisonHow PA's queue compares to PJM's — and where the new queue is headed

Three queue snapshots, side by side. PA's legacy active queue (the population this site analyzes), the PJM-wide 2022 queue at the time PJM closed it for reform, and the PJM-wide Cycle 1 queue announced April 29, 2026 — which is mostly natural gas. The state-level breakdown of PA projects within Cycle 1 has not yet been published; this site will be updated when it is.

Queue mix over time: PA legacy vs PJM legacy vs PJM Cycle 1

Share of MW capacity in each queue. Total queue size shown beneath the chart.
What the chart shows. PA's legacy active queue tracked PJM-wide closely on renewable share — both ran around 80–85% solar, storage, and solar+storage hybrids combined, with PA slightly more storage-heavy and slightly less gas-heavy. PA's queue also contained two utility-scale nuclear projects (both at Peach Bottom) that drive PA's 8% nuclear share. The Cycle 1 announcement reverses the pattern PJM-wide: the new queue is 48% natural gas, with solar down to 7%. Whether PA's Cycle 1 mirrors the system or holds onto its renewable mix is the question we expect to answer in coming weeks.

The case in briefPennsylvania has a permitting bottleneck and a federal countdown clock.

The bottleneck is what makes the policy necessary. The cliff is what makes the timing urgent. HB 502, with the right amendments, addresses both.

1.

The pipeline is real, vetted, and stuck

PJM has already determined these 91 projects can be safely interconnected and signed agreements with each developer. They are not waiting on engineering. They are waiting on bureaucratic process and politics. Most have been in development since 2018–2020.

2.

The federal cliff hits in 14 months

Under OBBBA, solar and wind projects must "begin construction" — meet IRS Notice 2025-42's Physical Work Test — by July 4, 2026, or be fully placed in service by year-end 2027. State and local permits are the binding prerequisite.

3.

HB 502's threshold misses the target

The bill's 25 MW eligibility floor was set as a generic "utility-scale" default. PA's pipeline is overwhelmingly community-scale. Lowering the threshold to 10 MW would expand HB 502's coverage of stuck projects from 29% to 83%.

103 GW authorized → 23 GW built

Per PJM's March 2026 disclosure, of the 103 GW of Generation Interconnection Agreements executed since 2020, only 23 GW reached commercial operation. 77% of GIA-posted projects withdrew before sending power to the grid. Permitting friction is the dominant attrition driver, and the federal cliff makes it worse.

Source: PJM, March 2026, via Heatmap, April 30, 2026
The PJM-wide queue mix has flipped

PJM's 2022 queue was 66% solar by capacity. The new Cycle 1 queue (April 2026) is 48% natural gas, with solar down to 7%. The state-level breakdown of Cycle 1 PA projects is forthcoming. The 91 PA projects already in legacy queue agreements remain the population most exposed to the federal cliff today.

Source: PJM Cycle 1 announcement (April 29, 2026), via Heatmap

Interactive mapThe 91 stuck projects, by county, and who represents them

Each PA county is shaded by total stuck capacity (signed PJM Interconnection Agreements, no commercial operation yet). Darker green = more MW. The number overlaid on each county is the count of ready-to-build projects there. We don't have parcel-level coordinates for individual projects — a single dot per project would imply more precision than we actually have. Use the controls to filter by fuel, status, or senator party — or to preview HB 502's eligibility threshold (the Policy section below walks through that analysis in detail). Click any shaded county to see every project in it and the regional representatives whose districts overlap.

HB 502 threshold preview

Drag to see which projects HB 502 would cover at each MW threshold. The project-count number on a county dims when none of its projects meet the threshold.

Capacity threshold ≥ 10 MW

Filter by fuel

Natural gas is not shown — there are 0 GIA-posted natural-gas projects in PA's queue. The 5 active gas projects are at the pre-GIA stage.

Filter by status

Filter by senator party

How to read the map: Each county's color reflects total stuck MW from ready-to-build projects (5 buckets, none through 125+ MW). The number overlaid is project count. The threshold preview slider above doesn't change county colors — it controls the label opacity, dimming counties where no projects currently meet HB 502's threshold. Drag down to 5 MW to see maximum coverage; up to 25 MW to see what the bill misses as currently drafted.

Largest projectsTop 20 GIA-posted PA projects by MW

Threshold analysisThe single most consequential amendment to HB 502

Lowering the bill's eligibility threshold expands coverage at every level of the development pipeline. The chart below shows three scopes — all 340 active PA projects, the 91 ready-to-build PA projects, and the 78 cliff-exposed solar/wind projects — at thresholds from ≥5 MW to ≥100 MW.

Projects covered by HB 502 at each threshold

Three scopes: full active pipeline, GIA-posted, and federal-cliff-exposed solar/wind
The 10 MW line is also defensible on first principles. Below 10 MW, PA solar projects typically operate as net-metered or distributed generation and fall under different regulatory frameworks. Above 10 MW, projects are unambiguously commercial-scale and reasonably subject to a state siting standard. The line is principled, not just convenient.

Counter-argumentsWhat the strongest critiques get right, and where they fall short

Three rebuttals to the case for amending HB 502 are worth taking seriously. None of them undermine the threshold-amendment argument, but each shapes how the policy should be drafted.

"Interconnection, not land use, is the bottleneck"

The MPL Law Firm critique (September 2025) argued that PJM's queue, not local zoning, was historically the binding constraint — and that PA's Municipalities Planning Code already imposes timing limits on local review.

What it gets right: for the 270 active PA projects still in PJM's pre-GIA pipeline, interconnection reform is the bigger lever.

Where it falls short: it doesn't apply to the 91 ready-to-build projects, which have already cleared PJM. For them, state and local permitting is the binding constraint by definition. The MPL critique is best read as "don't let HB 502 be your only reform," not "don't pass HB 502."

"They have GIAs — they'll get built"

It's true that an executed PJM GIA is a meaningful milestone. It's not true that it's a guarantee.

The data: per PJM's March 2026 disclosure, of the 103 GW of GIAs executed across all PJM since 2020, only 23 GW reached commercial operation. 77% of GIA-posted projects withdrew before sending power to the grid.

For PA's 78 cliff-exposed solar and wind projects, the historical attrition rate plus a hard federal deadline 14 months out is a worse setup than the 77% baseline implies. A state policy intervention is the only mechanism available to push the conversion rate higher.

"Local preemption is the wrong tool"

PA League of Cities and PSAB have raised concerns about HB 502's preemption of local land-use controls.

What it gets right: blanket preemption with no environmental safeguards or community-benefit floor would be a real problem.

Where it falls short: the bill as drafted already includes a 90-day RESET Board determination clock, a 45-day public hearing window, and a 180-day Environmental Hearing Board appeal window. The threshold amendment doesn't change any of those safeguards — it just expands which projects qualify for the same procedural framework. The MAREC and PEC testimony record makes the same point.

Political mapState legislators with stuck capacity in their districts

Almost every county with a GIA-posted project is represented in the State Senate by a Republican. The State House split is more competitive — both parties have districts with stuck capacity. These are the legislators whose constituents stand to gain construction trades jobs, host-community PILOT revenue, and tax base if these projects break ground — and lose it if they don't.

Hover or click any district above for details.

MethodologyHow this analysis works

Source data

PJM "Ready to Build" list (March 2026 snapshot — 495 projects across PJM with signed Interconnection Agreements but no commercial operation; sums to PJM's publicly-stated 54 GW figure). The 91 PA rows are the universe analyzed throughout this site. Broader PA active-queue context (340 projects, 10,421 MW) draws on the legacy Planning Queues file used in earlier versions of this analysis.

Active pipeline definition

Excludes Withdrawn, In Service, and Deactivated projects. Includes Active, Engineering and Procurement, Suspended, Under Construction, and Partially in Service — 340 PA projects, 10,421 MW summer-peak capacity.

GIA-posted urgent universe

Projects with executed PJM Generation Interconnection Agreements that have not yet reached commercial operation — i.e., signed agreements with PJM, ready to build. 91 PA projects, 1,758 MW. This is the population whose engineering review is complete and whose binding constraint is now state and local permitting. Source: PJM "Ready to Build" list (March 2026 snapshot).

Federal cliff exposure

Solar and wind projects only. Under OBBBA, these technologies must "begin construction" by July 4, 2026 (per IRS Notice 2025-42's Physical Work Test) or be placed in service by December 31, 2027. Standalone storage and nuclear are on the original IRA timeline through 2033 and are not directly cliff-exposed.

HB 502 threshold

Bill text uses "capacity," interpreted here as PJM's "MW Capacity" (summer net) field. For solar projects this typically runs lower than "MW Energy" (winter net), so the threshold semantics matter. Confirm with bill drafters before final use.

Legislator attribution

Each project is tagged with the State Senate and State House districts whose boundaries cover the project's county under PA's post-2022 redistricting. For projects pinned to county centroids (most), all overlapping districts are listed. Project locations are shown at jittered county centroids since precise lat/lon was not available in the source file. Where parcel-level coordinates are sourced, attribution becomes point-in-polygon and a single Senate + House district per project.

Cycle 1 mix shift

PJM's April 29, 2026 Cycle 1 announcement (811 projects, 220 GW system-wide) showed a dramatic shift in the PJM-wide queue mix: from 66% solar in 2022 to 48% natural gas today. The state-level breakdown of PA projects within Cycle 1 has not yet been published. The site will be refreshed when it is.

GIA-to-COD attrition

PJM's March 2026 disclosure: 103 GW of Generation Interconnection Agreements executed since 2020 produced only 23 GW of commercial operation — a 77% attrition rate. This is the historical baseline. For PA's 78 cliff-exposed solar and wind projects, the OBBBA tax-credit deadlines compress the construction window, making the attrition rate likely to run higher absent state policy intervention.

Limitations. This analysis covers the legacy PJM queue, which closed before April 2026. PJM's Cycle 1 — 811 projects, 220 GW system-wide — will produce a state-level breakdown in coming weeks. When that data lands, we will refresh this analysis to include both the legacy and Cycle 1 PA pipelines. The "stuck on permitting" inference for suspended projects is not yet directly verified; project-level outreach or FOIL requests would confirm.

DownloadsTake it with you